CW DUKE LTD LOGO | Building, refurbishment and fit out specialists

CASE STUDIES

Refurbishment & Fit Outs

Vintry Building, Bristol

SCOPE OF WORK

Vintry Building, located in the heart of Bristol used to be an open office space. The client wanted to redesign the office space and convert it into three separate office areas. The office needed a complete strip out and refurbishment. Redecoration, electrics and new flooring were installed.



HOW WE HELPED

Our team converted the open office into three separate areas. This was achieved by starting with a complete strip out of the existing space. All decorations, flooring and partitions were removed allowing our team to convert the office space.


Then, the office was divided into three separate areas comprising: collaboration spaces, individual desks and a kitchen space. This was achieved by using different materials so as each area had a different feel, new partitions were added where appropriate. Electrical works included installing separate distribution boards and additional air conditioning. Fixed booth seating was installed in the collaboration areas so as to create comfortable yet professional working areas.


 

THE RESULTS

Our team successfully converted the space into the three separate zones, making the space ideal for future tenants. The project was completed on time and the client was extremely satisfied with the quality of our work. 



Client: Ashville Asset Management Ltd. 

Timescale: 10 Weeks

Value: £200,000

Location: Bristol City Centre

Kings Court, Bath

SCOPE OF WORK

Tucked away on one of the many side streets off of Bath’s busy town centre, Parsonage Lane is where Kings Court is situated.

 

Built with the famous Bath Stone this office building has an instant style to attract businesses to call it their home. In need of a full refurbishment of their office floor areas, reception and amenities we have brought the office spaces back to life and full of character.  

 

Redecoration, new M&E throughout, flooring and internal features has ensured these offices are fit for purpose for many years to come. 


HOW WE HELPED

Though the location is perfect for the new tenants, it was more difficult from a construction point of view, so working closely with BANES our project team ensured we could get the access needed and keep to programme.


With tenants in situ, we did need to ensure our works, especially noisy works were timed to be the least disruptive, whilst allowing the important works to continue. 

 

THE RESULTS

Handing over a fresh new feel office space, makes this an ideal space for any new business to take on,

 

With the office areas being brought up to date and the amenities throughout being upgraded the interior finishes really make a difference to the atmosphere.

 

Our whole supply chain worked effectively throughout and the project was a complete success. 



Client: Project and Building Consultancy

Timescale: 29 Weeks

Value: £1.2m

Location: Bath

Gilbert House and 41 Corn Street, Bristol

SCOPE OF WORK

Situated on the bustling Corn Street in Bristol City Centre, we worked with IVRE and their team to completely transform Gilbert House and number 41.

 

Gilbert House is a 1930’s listed building which was full of art deco features. Based over 5 floors the building was in complete disrepair and required bringing up to date without losing any of its charming features that we could save.  

 

41 Corn Street is by contrast a 1960’s traditional office block, which required some care to bring back its ability to become useable, inspiring office spaces. 6 Floors of office space with a pleasant nod to its architecture of concrete and industrial feel with warmer tones and interior design.


HOW WE HELPED

These projects don’t happen without teamwork, and so working very closely with the whole project team, including Architects, Interior Design and project management this development has had an amazing transformation.

 

With works starting just a month before the COVID-19 pandemic our site team and sub-contractors worked in a safe and efficient way to deliver these two highly finished buildings.

 

THE RESULTS

We are proud to hand over two high quality office buildings within a prominent area of Bristol.

From keeping the original feel and character of the buildings to the small touches that bring them into the 21st century. This development has some real class about them, so much so that they already have new tenants who saw the potential straight away.

 

A selection of pictures to the right, but please also review our video and social media pages for more information on this project.

 

Corn Street Bristol - YouTube 


Client: IVRE

Value: £5m

Location: Bristol

The Woodworks Project, Roseberry Road

SCOPE OF WORK

The main aim of the project was to give this Charity a much needed new home. Our works included detailed alterations of the building to suit the Charity’s needs, including better access, layout and function.


The roof repair and general facia works allowed this Bath stone workshop to come to life.


Along with this a full M&E install, a lot of new walls and floor and a full decoration throughout ensured that the Charity’s goals were met. New paragraph



HOW WE HELPED

Working closely with the whole project team, allowed us to make sure that the internal space became a practical home for The Woodworks Project. We listened clearly to their needs and delivered the space they needed within the 20 weeks schedule.


With the building being in urgent need of repair we had to overcome many obstacles that the tired building threw at us, we problem solved and found the solutions with the help of our trusted supply chain. Everyone who worked with us on this project were determined to give the Charity this new space.



THE RESULTS

"Wow! Thank you CW Duke for such an amazing job! We really are looking forward to welcoming our clients to the new workshop”


This workshop now has the facilities to not only help produce the amazing woodwork projects they complete, but also carry on performing as a brilliant charity in the local area.  


Also see our YouTube channel: https://youtu.be/K8uqXAuOXEw


Client: Alpina Property Consultant LTD

Timescale: 18 Weeks               

Value: £402,000

Location: Bath, Somerset

Office and Battery unit exterior Wiltshire

Office Refurb & New Battery Build Unit

Project
Office Refurbishment
Timescale
32 Weeks combined
Value
£1.8m
Location
Wiltshire
CLIENTS REQUIREMENTS

Working with the renowned technology manufacturing company, we were employed to develop their requirements for a full refurbishment of their existing offices at their Malmesbury office and a new build on the newly formed Hullavington testing site.


Both of these projects were completed in early 2019. 

SCOPE OF WORKS
Office Refurbishment: Replace all Mechanical and Electrical works across the office, kitchen and WC’s. Provide access corridor to café, full office refurbishment including reconfiguration work and internal decoration

Battery Build Unit: Create a new battery build and test facility at the Hullavington site. Install M&E works including chillers, pumps, BMS and electrical connections. Civil and Structure works for hangers to allow for fit out of testing units. 
HOW WE HELPED
Working in a live environment we had to work with the estate and call centre team to ensure our works wouldn't affect the important customer service call centre. Works stuck to a strict schedule. 

The Hullavington site came with complexity due to the age and architecture of the large military hangers which were built in 1937.
THE RESULTS
The new open modern office floor, is now set up to take the team in Malmesbury forward. With lots of windows the office is very bright and has a calm feel to the décor. (Top Pictures)

Over in Hullavington the new unit is a perfect setting for the Research and Development of the battery units. (Bottom Pictures)
Brewhouse seating area refurbishment  Bristol

Brew House Project

Project
Commercial Office Refurbishment
Timescale
40 Weeks
Value
£1,900,000
Location
Bristol
REFURBISHMENT/FIT OUT

Due to our city centre location and previous working relationship with Edmond Shipway, it was only natural that they contacted us to competitively tender this exciting project in the heart of Bristol City Centre. We were then appointed based on our economically advantageous tender and our technical understanding of the project. 


The works consisted of the entire refurbishment of a four storey building to form commercial office accommodation. Our team performed minor internal demolitions including HVAC and M&E services. We then moved on to undertake fit out works to office, communal, reception, roof and toilet areas comprising new windows, flooring, wall and ceiling finishes. Also, we installed new M&E services inclusive of small power and distribution, fire alarm system, intruder alarm/CCTV, HVAC (VRF system) and data including Wi-Fi. Finally, we completed alterations and remodelling to the entrance area to the building, including installation of 5m high wrought steel gates.


The result is an amazing interior fit out, creating a new, contemporary and original building in the heart of Bristol City Centre.

PROGRAMME AND PROJECT MANAGEMENT
From the outset our client, Verve Properties, had a deadline for the completion of the works. Throughout the project, a number of variations and extras were added to the overall specification. Our dedicated team of trades people, sub contractors, site manager and contracts manager worked in partnership with the relevant stakeholders to adapt the programme to ensure that the project was still completed on time and the building was ready for letting when required.
DIRECTLY EMPLOYED TRADES PEOPLE
We utilised a number of directly employed trades people on this project. This ensured high standards and allowed us to adopt a flexible approach to the overall management of the scheme.
Regeneration and refurbishment of grade 2 listed building

RLAM, BROAD PLAIN

Project
Regeneration and refurbishment of Grade II listed building
Timescale
20 Weeks
Value
£1,100,000
Location
Bristol
CLIENTS REQUIREMENTS
In a conservation area of Bristol, RLAM need to release the asset of 4 storey office building which was in need of refurbishment, internally and external to make it desirable office space. This would fit with the already fully let phases 1&2.  
SCOPE OF WORKS
Full CAT – A refurbishment, including common parts and the provision of a new extension at the rear of the building. This would serve as the new main entrance and reception. This required piled foundations and alterations of underground services runs. Project management, full strip-out, structural. 

Due to restricted heights M&E installations were all visible meaning that the workmanship had to be of the highest quality. This work now means that each floor is served independently by electrical and mechanical installations, including VRF heating and cooling to the mansard level, wet heating all other areas along with fresh air ventilation. 

The common parts refurbishment, included the complete reconfiguration of WC facilities and the introduction of a new modern glass and oak balustrade system to the main stairwell.

Replacement of the existing life car was replaced entirely to meet the new standards
HOW WE HELPED
Across 18000ft2 office space and common areas we had to programme the disciplines effectively to work through all the areas. 

This building hadn’t seen any improvements of any significance from a number of years which meant upon stripping out existing installations we had to overcome some challenges quickly. We worked closely with the design team to provide the solutions to maintain our progress on the project, whilst preserving the quality throughout. 

The external works were undertaken meticulously to ensure the full satisfaction of the conservation officer. 
THE RESULTS
A complete transformation of the building inside and out within challenging timescales.

The building has maintained its period feel and character from the outside whilst undergoing a significant transformation internally offering flexible commercial office space to appeal to all markets. 
the Pigsty restaurant t seating area Bristol

The Pigsty Restaurant, Gloucester Road

Project
New Restaurant
Timescale
8 Weeks
Value
£256,,000
Location
Bristol
CLIENTS REQUIREMENTS

A brand new 80 cover restaurant for the popular restaurant brand “Pigsty Restaurant UK Limited” who already have a successful restaurant Cargo 1. 

Working with Contract Administrator CS2 Limited to help deliver and drive the project. 

SCOPE OF WORKS
Our main requirements for this project were; 
• Full strip out of Existing fit out
• Extensive M&E work to include a fully service bar and high tech kitchen
• Keep and retain original features within the unit
• Create new WC facilities 
• Full decoration throughout
• Fit out of furniture and equipment 
HOW WE HELPED
Working really closely with the contracts team and the owners of the Pigsty we worked to the vision they had for their restaurant, this included a few variations mid-way through the project which we adapted too. 

With the restaurant open day set, our directly employed team and sub-contractors had to work to a tight schedule. 

The on-site team worked hard to keep the original features. 
THE RESULTS
A contemporary, bright, spacious restaurant with lots of character and charm. 

The open days of the restaurant and the new menu has been a big success.  
Lomand House exterior Newbury office refurbishment

Lomand House

Project

Office Refurbishment

Timescale
17 Weeks
Value
£775,000
Location
Newbury, Berkshire
CLIENTS REQUIREMENTS
A leading healthcare provider across the UK and Ireland knew they wanted a full refurbishment of their office based in Newbury, Berkshire. 

Having originally been constructed in 2000 the ‘L’ shaped office block spread over 3 storeys was in need of bringing back up to date with extensive refurbishment. 

With 50% of the block in occupancy CW Duke were required to ensure all adjoining offices could continue to function as normal. 
SCOPE OF WORKS
• Project management, of full removal of all fixtures, fittings, including carpets and ceilings (All to be replaced with new)
• Toilets and tea points fully fitted 
• Extensive replacement of Mechanical and Electrical services
• Lift Refurbishment
• Renovation of existing fabric and external walls
HOW WE HELPED
Working very closely with the full project team we ensured we were achieving the office the client had visualised at the beginning of the project. 

Due to the adjoining offices being fully occupied we had to ensure that noise, disruption and construction traffic was under full control and always to a minimum throughout the whole project. 

With the extensive Mechanical Service required CW Dukes ensured that our communication, time-frames and results were communicated with both the client and the specialist M&E consultant. 
THE RESULTS
On hand over of this project the results were amazing delivering the client a bright, clean, open plan office suite. 

Internally brought back into a position to service a busy office which will last. 